We are pleased to advise that the New EMR Delivery Body Portal is now open for registration. You can access the New EMR Portal by visiting the New EMR Delivery Body Portal webpage and clicking on the New EMR DB Portal Log In button. Please see Latest News article published 22 Jan 2024 for further details. T1 2024 2025 and T4 2027 2028 CANs have now been released. The CfD Application Assessment Window for AR6 and results will be released on the 20th May 2024
SharePoint
  • add link
  • add page
  • close

    ​​​​​

    Prospective CMUs

    Prospective CMUs (New Build and Refurbishing CMUs) must provide regular progress updates to the Delivery Body. These CMUs also need to achieve Financial Commitment and Substantial Completion Milestones.

    Construction Progress 
    Reports

    Prospective CMUs must provide periodic construction progress update reports until either the Substantial Completion Milestone has been achieved, the Capacity Agreement terminates or a Non-completion Notice has been issued.

    ​​​Milestones​

    Prospective CMUs must achieve Financial Commitment Milestone to demonstrate commitment to Capital Expenditure or funding and, Substantial Completion Milestone (SCM) to demonstrate the generating capacity.  If a CMU cannot demonstrate that it has achieved SCM it must provide details of Minimum Completion Requirements (guidance on this can be found in the SCM guidance document).

    3-monthly and 9-monthly reports  

    These reports outline Construction Milestones, non-technical summary and any changes to dates or works. These reports are not required to be accompanied by Independent Technical Expert assessment.

    ​Financial Commitment Milestone (FCM)​

    ​​​​To achieve FCM, the CMUs must submit an Independent Technical Expert report, Directors Certificate and a Funding Declaration (Exhibit J) to the Delivery Body by the deadline stated in the Capacity Market Rules.

    Link to Guidance Document​ (​​Section G.9 of Prequal Guidance)​

    Link to Directors Certificate template

    Link to Funding Declaration (Exhibit J) template

    6-monthly reports 

    These reports need to be provided every 6 months (by 1 June and 1 December) until Substantial Completion Milestone has been achieved. These reports must only be accompanied by an Independent Technical Expert assessment if there have been any Material Changes to the works.

     

    Link to Guidance Document​

    Substantial Completion Milestone (SCM)​

    To achieve SCM, Prospective CMUs must demonstrate that they have been commissioned (or recommissioned) and are operational at/above 90% of their Capacity Obligation. Prospective CMUs should also have completed a Metering Assessment (and submitted a Metering Test if applicable) and have provide detailed line diagrams.

    If a CMU holds an Agreement for more than 1 Delivery year, an additional ITE Report is also required to confirm Total Project Spend. Where an agreement is for more than 3 Delivery years, an ITE Certificate is also required confirming that the CMU has met the Extended Years Criteria.

    Link to Guidance Document​

    Link to Appendix A1 (Distribution CMU)

    Link to Appendix A2 (Transmission CMU)

    Link to Appendix B1 (Capital Expenditure)​